The client in Russia, had an urgent requirement for the vertical development of 2 ore passes and 2 ventilation raises.
Master Detra used raise boring to drill/bore the 2 ventilation shafts. Master Detra utilized raise boring technology to excavate the ore passes and ventilation raises.
The project was successfully completed in time, despite the impacts of protocols introduced due to Covid-19. The client was very pleased with our operations.
Machine | Master Drilling RD3A-250 with hands-free rod handling system |
Excavation depth (m) | 93m to 132m |
Diameter | 2.4 m diameter |
Geology | Gabbro, solid beds, stable |
Project Owner | JSC Kolskaya Mining-and-metallurgical integrated works (subsidiary of PJSC Norilsk Nickel), Severnyy-Glubokyy (North-Deep) Mine, Zapolyarnyy town. |